Battersea Rise, London SW11 1HS
A severe storm caused a large tree to collapse on to the sports hall / changing room roof damaging both internal and external structural elements. JWC had to erect scaffolding and work with structural engineers to replace steel beams and structural roof supports together with new sheeting. This also involved the renewal of internal electrics, re plastering and re decorating the affected areas.
At the same time we were asked to redesign and refurbish the boys and girls changing room areas with new purpose made hardwood benching and racking with new specialist flooring and redecorate on completion. Works completed within a set 8 week period.
Works involved – renewal of damaged sports hall roof
Works involved – new changing rooms